The World Bank sent a letter to Treasury Cabinet Secretary John Mbadi, Roads and Transport Cabinet Secretary Davis Chirchir and Lands Cabinet Secretary Alice Wahome raising concerns over stalled compensation for the Horn of Africa Gateway Development Project’s Isiolo‑Mandera highway.

World Bank Division Director Qimiao Fan noted that although credit proceeds have been available since 2024, the compensation process only began in November 2025 and remains limited to the Isiolo‑Modogashe section.

Fan warned that each month of delayed site possession adds roughly KSh1 billion in recurring costs—covering supervision, security, idle equipment and personnel—and an additional KSh207 million for equipment demobilisation and remobilisation.

The bank highlighted that only 1,281 of the 1,669 identified project‑affected persons have received compensation, underscoring the slow pace of payments.

On the Isiolo‑Kulamawe stretch, the Kenyan government has paid KSh456 million in compensation, yet the World Bank estimates a monthly exposure of KSh536 million if delays continue.

The Wajir‑Tarbaj‑Kotulo section, slated for completion of compensation by November 2026, is also lagging, with projected extra costs of KSh421 million per month.

The 740‑kilometre highway is currently 60 percent complete as of 26 October and was originally due for completion in January 2028, a deadline now pushed to around 2030.