The Port Authority of New York and New Jersey is shifting its strategy toward a full replacement of the Outerbridge Crossing, following an engineering feasibility study that found widening the existing bridge would be almost twice as expensive and take nearly twice as long as constructing a new crossing.
The study, titled the Outerbridge Crossing Widening Feasibility Study’s Scheme Development Package and dated 30 September 2026, was prepared for the Authority by HDR and its engineering team.
Engineers examined whether the four‑lane bridge could be expanded to six lanes, meet modern highway standards and include a shared‑use path, but identified that the bridge’s structural components lack sufficient reserve capacity for the additional loads.
Two preliminary widening schemes – a symmetrical expansion on both sides (Scheme S2) and an asymmetrical expansion on the northern side (Scheme A2) – were evaluated, each requiring extensive reinforcement of foundations, piers, bearings, trusses and girders.
The analysis indicated that roughly 57 % of north‑truss members under Scheme S2 and 55 % under Scheme A2 would need major strengthening, involving reinforcement plates and replacement of thousands of rivets.
Projected construction timelines show that the strengthening work alone could exceed five years, with overall staging potentially causing roadway closures and impacts on motorists for up to eight years.
The feasibility report also notes that widening could affect up to 33 nearby properties and existing utility networks, and would limit future improvements to the Arthur Kill navigation channel due to fixed pier locations.
Under its approved 2026–2035 Capital Plan, the Authority has allocated $336 million for a four‑year rehabilitation of the existing bridge to keep it operational while planning for a replacement in the 2036–2045 capital period.
The study does not set a final cost or construction start date for a replacement, but confirms that the Authority’s immediate priority is maintaining the current crossing and advancing replacement planning.