The Ministry of Industry and Trade said the Ninh Thuan 1 nuclear plant is now slated to begin operations in 2037‑2038, moving the original 2030‑2035 window forward by several years.
For the second unit, Ninh Thuan 2, the ministry indicated an operational window of 2039‑2040, although the investor Petrovietnam has suggested an earlier 2035‑2036 target if conditions allow.
Both projects each comprise two reactor units; Ninh Thuan 1 units are designed for 1,200 MW each with Russian partner Rosatom, while Ninh Thuan 2 units are planned at 1,455 MW each using South Korean technology.
Vietnam Electricity Group (EVN) has submitted a pre‑feasibility study for Ninh Thuan 1 to the Ministry of Finance, and Petrovietnam is conducting a similar study for Ninh Thuan 2.
The ministry’s assessment, based on Russian and planning consultancy estimates, suggests a minimum 12‑year period from feasibility study to commercial operation, underpinning the 2037‑2038 target for Ninh Thuan 1.
EVN continues to propose an accelerated schedule of 2034‑2035 for Ninh Thuan 1, contingent on favorable policy mechanisms and investment frameworks.
The revised Power Development Plan VIII, approved in February 2025, originally projected both nuclear plants to be operational between 2030 and 2035 with a combined capacity of 4,000‑6,400 MW.
Under the new scenario KB2A, the ministry envisions total nuclear capacity of about 30,771 MW by 2050, requiring roughly $187.3 billion in capital from 2026‑2050.
The ministry also plans to study special investment mechanisms, human‑resource development, and infrastructure support, while reviewing potential northern sites to ensure a stable long‑term base‑load supply.