Poland’s state‑owned nuclear developer Polskie Elektrownie Jądrowe (PEJ) and the US‑based Westinghouse‑Bechtel consortium signed a letter of intent on 19 November 2026 to broaden their engineering development agreement and start additional procurement for the first reactor’s long‑lead items.

The agreement targets the three‑reactor, $50 billion project at Lubiatowo‑Kopalino on Poland’s Baltic Sea coast, which will house three Westinghouse AP1000 units delivering about 3,750 MW in total.

Westinghouse and Bechtel will coordinate the purchase of long‑lead components and engage export‑credit agencies to secure financing for those supplies, aiming to lock in manufacturing capacity that can take years to produce.

Earlier, in October 2026, PEJ authorised Westinghouse to order six key components for the first reactor’s nuclear island, including the containment vessel and structural modules.

Four Polish firms – Energomontaż‑Północ Gdynia, FAMAK, Mostostal Kielce and Mostostal Kraków – have received conditional purchase orders for prefabricated wall and floor modules, pending compliance with nuclear quality‑assurance standards.

Japan’s IHI Corporation also secured an order from Westinghouse for engineering and procurement of long‑lead items for a containment vessel and a large steel module for the first unit.

Site preparation at Lubiatowo‑Kopalino, overseen by Bechtel since August 2026, includes grading, drainage, temporary roads and geological surveys, setting the stage for the main construction phase.

PEJ applied for a nuclear construction permit in March 2026 and plans a separate building‑permit filing in 2027; the first concrete pour is targeted for Q4 2028, subject to regulatory clearance.

If the schedule holds, the first reactor could start commercial operation in 2036, followed by the second in 2037 and the third in 2038, eventually supplying roughly 10 % of Poland’s electricity demand.