KenGen announced a target to install 250 MW of new renewable capacity by 2027 to reinforce the national grid and support industrial growth.

The company’s Managing Director and CEO Eng. Peter Njenga said the plan relies on expanding geothermal, solar and hydroelectric generation, while also assessing wind and floating‑solar options.

At the KenGen Sustainable Energy Conference 2026 in Olkaria, Njenga confirmed the rehabilitation of the 63.3 MW Olkaria I geothermal plant is complete and will be commissioned by President William Ruto on 7 December.

KenGen has finished evaluating EPC contractors for a 42.5 MW solar plant to be co‑located with its Gogo hydro station, which itself will add 8.6 MW of power.

An 80.3 MW geothermal project is also progressing toward grid connection, and feasibility studies are under way for a 26 MW small‑hydro scheme at Nabuyole in Webuye.

KenGen is eyeing wind development in Marsabit, where wind speeds could support up to 1 000 MW, starting with a 200 MW pilot.

To fund these projects, KenGen is seeking roughly US$12 billion, engaging lenders such as KCB Group and Stanbic Bank.

KenGen’s broader pipeline envisions 5 540 MW of new renewable capacity by 2034, of which the 250 MW target is the first milestone.

More than 90 % of KenGen’s existing 1 786 MW capacity is renewable, yet the utility believes Kenya has tapped only a small share of its estimated 10 000 MW geothermal potential.

Investors are already developing projects within KenGen’s Green Energy Park in Olkaria, a designated special economic zone offering tax incentives, including a 165 MW geothermal‑powered green fertiliser plant that could create over 2 000 jobs.

KenGen also continues discussions on nuclear options, seeking suitable technology partners and public‑private models to attract private capital.