The single‑terminal redevelopment at St. Louis Lambert International Airport has been delayed while airport officials negotiate higher construction costs with airline partners.

Airport interim director Gerald Beckmann told the St. Louis Business Journal that the revised 30% design package is now targeted for agreement in the first quarter of 2027.

Initial estimates placed the project between $2.8 billion and $3 billion, but officials have not disclosed a revised budget as negotiations continue.

Beckmann identified higher fuel, steel and glazing prices as key drivers of the cost increase, though he declined to reveal the percentage rise.

The airport originally proposed consolidating its two existing terminals into a single modern facility with a 60‑gate vision, but the final gate count remains under review for affordability.

Lambert currently operates 46 gates, a mix of airline‑leased and city‑controlled facilities.

Southwest Airlines, the airport’s largest carrier by passenger volume, is expected to shoulder the largest financial contribution through revised airport rates and charges.

The existing use‑and‑lease agreement with airlines expires on 30 June 2027, prompting the need for a new financial framework before construction can proceed.

Federal infrastructure support, such as the proposed $30 billion Modern Skies Act championed by Senator Eric Schmitt, could provide additional funding, although Lambert has not confirmed any allocation.

Enabling works—including a new utility plant, $180 million in federal funding for site preparation, and other preliminary projects—have been secured, but the main terminal construction start date remains undefined.