Houston‑based developer EmberClear announced a combined‑cycle 1.4 GW natural‑gas power plant that will occupy about 137 acres of the Fay‑Penn Business Council property in Dunbar Township.

The power plant will be part of a larger industrial complex that includes a 28.3 million‑square‑foot data‑center site covering roughly 650 acres east of the plant parcel.

Both parcels are already zoned for light industrial (M‑1) use, eliminating local zoning hurdles for the development.

EmberClear expects to make a final investment decision by 2028, with commercial operation of the plant projected for the second quarter of 2031.

The site already has water, sewer and natural‑gas services nearby, and six major pipelines connect to a gas hub two miles away, supporting the plant’s fuel supply.

EmberClear has entered PJM’s Cycle 1 interconnection queue and is pursuing air‑emission permits, while an engineering, procurement and construction contractor has been secured.

Local officials said the township was only briefed on the project during a lunch meeting on Thursday, highlighting a communication gap between EmberClear and municipal leaders.

Township board chairman George Stash noted that, because the sites meet all legal requirements, the township cannot deny the project aside from a storm‑water agreement.

County and state regulators, including the Pennsylvania Department of Environmental Protection and the U.S. EPA, will oversee pollution and air‑quality monitoring for the plant.

EmberClear officials plan to attend a Fayette County board meeting on Dec. 11 to discuss a proposed data‑center ordinance, though no data‑center tenant has yet been secured.