The Western Downs Digital Park, a proposed artificial‑intelligence data centre in Queensland, has attracted 595 objections out of almost 600 public submissions, with only two supporting the development and one neutral response.

The project is being led by Singapore‑based Zerra DC, which has named US AI firm Anthropic as the anchor tenant for the facility.

Located about 250 km west of Brisbane, the 725‑hectare site lies roughly 37 km northwest of Dalby and is within 600 m of the Braemar 275 kV/330 kV transmission substation.

The centre’s initial phase is planned to deliver up to 1.44 GW of IT capacity, with a peak electricity demand of 2.16 GW across four phases, potentially consuming about 47 GWh per day – comparable to the daily usage of 1.5 million Australian households.

Zerra DC says the campus will connect directly to the high‑voltage grid via customer‑owned switching stations, bypassing the local distribution network, though additional generation, transmission capacity and storage may still be required.

Residents have highlighted water usage, noise, traffic and pressure on local roads and housing, prompting the developer to propose air‑cooling, rainwater harvesting and treated‑wastewater reuse to limit reliance on the town’s potable supply.

A Climate Council analysis estimates the centre could emit about 8.3 million tonnes of CO₂‑equivalent annually by 2035 if its electricity demand is not matched by additional renewable generation.

Zerra DC has pledged to expand community engagement and report on any changes requested by residents, while Anthropic declined to comment on the opposition.

The development application remains under assessment by the Western Downs Regional Council, with the public consultation period having closed on 11 November 2026.

The strong community response mirrors recent setbacks for other large data‑centre projects in Australia, such as the Goodman Group’s abandoned Sydney plan and NextDC’s delayed Melbourne proposal.