The West Virginia Public Service Commission gave final approval on 17 November 2026 for the Maidsville Energy Center, a $2.48 billion natural‑gas power plant to be built in Monongalia County.
Monongahela Power Company and The Potomac Edison Company will develop the 1,200 MW combined‑cycle facility on roughly 35 acres adjacent to the existing Fort Martin Power Station.
The approval also covers three solar sites that together will add 70 MW of renewable capacity, with an estimated investment of $182 million.
Construction can begin in 2027 after a minimum 30‑day notice, submission of verified engineering documents, and compliance with daytime‑only blasting and pile‑driving restrictions; the certificate lapses if work does not start within five years or is not completed within ten years without regulator consent.
FirstEnergy plans to sign an EPC contract in Q4 2026, secure a long‑term natural‑gas supply agreement, start site preparation in early 2027, and bring the plant into commercial operation by 31 December 2031.
The project’s demand forecast is tied to a large data‑center customer, whose anticipated capacity need is projected to rise from 100 MW in 2028 to 1,012 MW by 2033, a figure contested by consumer and environmental groups.