President William Ruto said the government will commence the ground‑breaking ceremony for the Muthaiga‑Kiambu road expansion in the first weeks of 2027, after completing the procurement process.

The project, valued at Ksh38 billion, will convert the existing 27‑kilometre stretch into a four‑lane dual carriageway, extending from Pangani through Ridgeways, Windsor and Runda to Kiambu Town and Ndumberi.

Design features include two service lanes on each side, new bridges at Muthaiga Golf Club and Kirigiti Junction, and overpasses at Mua Road and Tala Road.

Additional elements comprise U‑turns at Coffee Garden, Ridgeways and Runda, dedicated pedestrian and cyclist lanes, six footbridges, interchanges and connecting bypasses.

The National Land Commission has issued notices to landowners along the route, seeking acquisition of 11 parcels on behalf of the Kenya Urban Roads Authority to enable the expansion.

Landowners are instructed to visit the NLC office at Ardhi House in Nairobi to review maps indicating the specific land portions earmarked for acquisition.

Ruto also highlighted that more than 411 kilometres of roads are under construction across Kiambu County, with a total allocation of Ksh60 billion for these projects.

He noted that the previously stalled Mau Mau road projects have progressed to 80‑90 per cent completion, up from 20 per cent when the current administration took office.