The National Assembly Departmental Committee on Energy and Petroleum questioned the accountability of the first crude oil consignment from Lokichar, scheduled for December 2, 2026, and asked for transparency in compensation to affected communities.

Principal Secretary for Petroleum Kello Harsama confirmed that about Sh2.7 billion has been released to the National Land Commission for compensation, but committee chair David Gikaria warned that unverified payouts could delay the shipment.

Harsama also clarified that a multi‑agency team from the State Departments of Petroleum, Interior, Roads and Water is coordinating security and logistics along the transport corridor.

Harsama rejected claims of favouritism, stating that international suppliers such as Saudi Aramco, ADNOC and ENOC nominate their Kenyan partners and the government does not appoint any company.

MP Gikaria urged the ministry to publish detailed information on the arrangement to dispel rumours of share allocations and to improve public understanding of its commercial framework.

The proposed distribution of 187,000 LPG cylinders to low‑income households was examined, with MPs seeking assurance that cylinders stored for years are safe before release.

Harsama said responsibility for the LPG programme now rests with the National Oil Corporation of Kenya and that cylinders must undergo standard eight‑year revalidation tests, a process for which funding has been requested through Supplementary Budget I.

Finance officer Dismas Ogot proposed converting the Petroleum Development Levy into a reserve fund to cushion the sector against unexpected financial pressures, replacing the current ad‑hoc use for fuel price stabilization.

Gikaria cautioned that any changes must protect the statutory funds created under the Petroleum Development Levy Act of 1991, which finance petroleum infrastructure and stabilization interventions.

In the energy sector, Principal Secretary Alex Wachira reported Kenya’s peak electricity demand rising to 2,559 MW, prompting tests of imports from Ethiopia of 350‑400 MW during low wind periods and the commissioning of a refurbished 63 MW Olkaria I geothermal plant on December 7, 2026.

The committee was also briefed on outstanding electricity debts, with Nairobi County owing roughly Sh6.7 billion, and on Kenya Power’s consideration of disconnection measures for defaulters, prompting a tripartite engagement to resolve payments.

Energy agencies highlighted funding shortfalls affecting nuclear power preparations, geothermal drilling and rural electrification, noting that the nuclear programme is behind schedule and that the Geothermal Development Company is seeking supplementary budget allocations to bridge its development gap.