The Committee on Housing, Urban Planning and Public Works highlighted that delays in issuing title deeds for affordable‑housing projects could jeopardise Kenyans’ ability to own homes they have already paid for.

The issue was examined in a committee meeting chaired by Vice Chairperson Hon. Rindikiri Mugambi, where officials from the National Land Commission (NLC) were called to account.

Dr. Samuel Mwenje, NLC Director of Land Administration and Management, said the commission had issued 12 letters of allocation for previously unalienated public land parcels and processed 11 consents to transfer land already registered under other public bodies.

He attributed further delays to the lack of comprehensive land reports and supporting documentation from the Affordable Housing Board, noting that each parcel requires distinct planning and legal steps.

Hon. Mugambi urged the commission to accelerate the process, stressing that without proper documentation Kenyans cannot claim ownership of a house or even a floor.

Committee members also raised concerns about the gap between the roughly 1.4 million programme subscribers and the 18,000 houses actually allocated to date.

Specific cases such as the Nanyuki affordable‑housing project were cited, with MPs questioning why completed houses had remained unallocated for almost two years.

Dr. Mwenje acknowledged that the speed of engagement with the Affordable Housing Board had been a challenge, contributing to the backlog.

To resolve the outstanding issues, the committee resolved to hold a joint meeting with the NLC, the Affordable Housing Board and the Principal Secretaries for Lands and Housing.