The New South Wales Land and Environment Court dismissed Verdant Earth Technologies' appeal against the Independent Planning Commission’s 2025 decision to refuse the Hunter Valley Biomass Power Project, leaving the proposal without planning approval.

The project aimed to convert the former Redbank coal‑fired power station near Singleton into a 151 MW biomass generator, which Verdant Earth said would supply electricity to roughly 200,000 homes.

Verdant Earth proposed using about 700,000 tons of dry biomass each year, sourced from invasive native species cleared under government programmes and from purpose‑grown crops.

While the Independent Planning Commission acknowledged potential benefits for electricity reliability and regional employment, it concluded that the environmental impacts of the fuel strategy outweighed those benefits.

Environmental groups warned that demand for invasive vegetation could incentivise further land clearing, threatening wildlife habitats and endangered species.

Verdant Earth maintains that most feedstock would come from approved clearing programs and that it has revised the plan to reduce reliance on invasive species.

The project was projected to create around 330 construction jobs and 60 permanent positions during operation.

The court’s ruling also affects a separate data‑center proposal on adjacent land, which had been discussed with Voltic DC for shared infrastructure and electricity supply.

Verdant Earth CEO Richard Poole said the company will reassess its options, including possible legal avenues or alternative developments such as a data centre or battery storage facility.

Despite the setback, Verdant Earth indicated it is not abandoning its ambitions for the Redbank site, though the future of the biomass conversion remains uncertain.