ENGIE, Aeolus and Orascom Construction announced that the 900 MW Shokeir wind farm in Egypt has achieved financial close, securing roughly $588 million of non‑recourse debt on 12 November.
The consortium’s equity split assigns 35 % of the project company to ENGIE, 40 % to Aeolus and 25 % to Orascom, which will also handle civil and electrical balance‑of‑plant works.
Funding comes from a mix of international lenders, including Japan’s JBIC, France’s PROPARCO, the Netherlands’ FMO, Société Générale, Crédit Agricole CIB, Germany’s KfW IPEX‑Bank and insurance from NEXI.
The project will operate under a 25‑year power purchase agreement with the Egyptian Electricity Transmission Company, providing a predictable revenue stream for the non‑recourse financing.
Construction began in June 2026, with the wind farm slated to connect to the grid in three phases; the first 300 MW is scheduled for commissioning in January 2028 and full capacity is expected by summer 2028.
When fully operational, the farm’s 86 Goldwind turbines of 10.5 MW each will supply electricity to more than 1.4 million households and avoid roughly two million tonnes of carbon emissions annually.
ENGIE Egypt chief executive Mohamed Awni highlighted that the financial close underscores the strength of the partnership and will nearly double the consortium’s wind capacity in Egypt, raising it from 912.5 MW to about 1.8 GW.
The project’s timeline slipped slightly, reaching financial close about four months later than the early third‑quarter target set in March, with a cabinet licence now pointing to a November 1 2028 completion date.