Applied Digital confirmed that the first 25 MW data hall at Polaris Forge 2 has been fitted out and declared ready for service, completing the base‑build commissioning of the first 75 MW of the 150 MW facility.
The 150 MW building is constructed in two 75 MW phases, each comprising three 25 MW halls that are tested together; the first phase is now commissioned with one hall operational and the remaining 50 MW of that phase slated for fit‑out and delivery.
The entire Polaris Forge 2 building is already fully leased under a 200 MW long‑term agreement with an unnamed hyperscale customer, representing roughly $5 billion in contracted rent over about 15 years.
Applied Digital noted that the $5 billion figure reflects expected rental revenue, not construction costs, and that its total portfolio now carries more than $41 billion in contracted base‑term lease revenue.
Future expansion plans remain variable: an August 2025 plan cited a $3 billion, 280 MW campus, while later releases mentioned 300 MW across two 150 MW buildings and some industry forecasts suggest the site could eventually reach 1 GW.
The next steps involve fitting out the remaining two halls of the first 75 MW phase and then moving to commissioning the second 75 MW phase, a schedule critical because hyperscale tenants pay only when capacity is ready.